Wednesday, July 4, 2007



June 30-July 3: Initial plumbing finished. The only thing worth seeing so far is the tub/shower unit in the upstairs bathroom. It is a one-piece Aqua Glass unit. It was a little tricky to get upstairs, but they managed it OK.
Posted by owl_at_home at 8:38 PM

No comments:

Post a Comment

Newer Post Older Post Home
Subscribe to: Post Comments (Atom)

Blog Archive

  • ►  2008 (5)
    • ►  January (5)
  • ▼  2007 (45)
    • ►  December (3)
    • ►  November (5)
    • ►  October (7)
    • ►  September (4)
    • ►  August (6)
    • ▼  July (8)
      • July 15: Here is a window that we got to go in the...
      • July 15: Here are some more pictures of the porch...
      • July 13: Roofing started. Shingles are on the bac...
      • July 11: Posts started going up around the porch. ...
      • July 10: Porch frame and floor completed. We will ...
      • July 4: Decking and tar paper on the roof were com...
      • July 3: Temporary stairs built! The frame of the s...
      • June 30-July 3: Initial plumbing finished. The onl...
    • ►  June (12)

About Me

owl_at_home
View my complete profile